1.If A can do a piece of work in n days, then A's 1 day work=1/n


2.If A's 1 day's work=1/n, then A can finish the work in n days.


Ex: If A can do a piece of work in 4 days,then A's 1 day's work=1/4.
If A's 1 day’s work=1/5, then A can finish the work in 5 days


3.If A is thrice as good workman as B,then: Ratio of work done by
A and B =3:1. Ratio of time taken by A and B to finish a work=1:3


4.Definition of Variation: The change in two different variables follow some definite rule. It said that the two variables vary directly or inversely.Its notation is X/Y=k, where k is called constant. This variation is called direct variation. XY=k. This variation is called inverse variation.


5.Some Pairs of Variables:

i)Number of workers and their wages. If the number of workers increases, their total wages increase. If the number of days reduced, there will be less work. If the number of days is increased, there will be more work. Therefore, here we have
direct proportion or direct variation.

ii)Number workers and days required to do a certain work is an example of inverse variation. If more men are employed, they will require fewer days and if there are less number of workers, more days are required.

iii)There is an inverse proportion between the daily hours of a work and the days required. If the number of hours is increased, less number of days are required and if the number of hours is reduced, more days are required.

Share |

Labels:

Time And Work Practice Problems

Posted by Ravi Kumar at Thursday, February 12, 2009
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Time And Work Practice Problems:

For Time And Work concept click: http://business-maths.blogspot.com/2008/08/time-and-work.html

For Time And Work solved problems click: http://business-maths.blogspot.com/2008/11/time-and-work-problems.html

Practice Problems:

1.If 20 men take 30 days to complete a job.In how many days can 25 men complete the job?
a)28 days b)24 days c)36 days d)20 days

2.Fifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days?
a)20 days b)8 days c)9 days d)10 days

3.A piece of work can be done by 16 men in 8 days working 12 hours a day.How many men are needed to complete another work, which is three times the first one,in 24 days working 8
hours a day?
a)24 men b)29 men c)20 men d)30 men

4.A can do a piece of work in 9 days.,B can do the same in 12 days.In how many days can the work be completed if A and B work together?
a)5 1/9 days b)5 1/4 days c)5 1/3 days d)5 1/7 days

5.A and B together can do a piece of work in 12 days and A alone can complete the work in 18 days. How long will B alone take to complete the job?
a)30 days b)36 days c)6 days d)56 days

6.Anil and Amit can complete a job in 12 days working together. Amit alone can complete it in 16 days.Both of them worked together for 4 days and then Amit left. How long will Anil take to complete the remaining work?
a)30 days b)47 days c)32 days d)24 days

7.A and B can do a piece of work in 12 days,B and C can do it in 15 days and C and A can do the same work in 20 days. How long would each take to complete the job?
a)1/30,1/20,1/60 b)1/20,1/30,1/30 c)1/20,1/20,1/20 d)1/60,1/0,1/30

8.A and B can do a work in 12 days,B and C in 15 days and C and A in 20 days.They all work together for 6 days and then A left.In how many more days can B and C finish the remaining work?
a)5 days b)6 days c)8 days d)9 days

9.A can do a work in 12 days.When he had worked for 3 days B joined him.If they complete the work in 3 more days.In how many days can B alone can finish the work?
a)5 days b)6 days c)8 days d)9 days

10.A and B together can do a piece of work in 14 2/5 days;B and C together can do the same work in 12 days.After A worked for 8 days,B for 12 days C takes up and finished it alone in 6 days.In how many days will each of them do the work,working alone?
a)28 days b)24 days c)36 days d)20 days

11.To do a certain work C alone takes twice as long as A and B together.A would take 3 times as long as B and C together.All three together complete the work in 5 days.How long would each take separately?
a)15 days b)29 days c)20 days d)10 days

12.4 men or 5 women can construct a wall in 82 days.How long will it take 5 men and 4 women to do the same?
a)30 days b)47 days c)32 days d)40days

13.If 9 men and 12 boys can do a piece of work in 4 days and 4 men and 16 boys can do the same piece of work in 6 days.how long will 6 men and 24 boys take to complete the same work?
a)5 days b)6 days c)8 days d)4 days

14.A certain number of men can do a work in 20 days.If there were 4 more men,the work can be done in 5 days less.How many men were there initially?
a)12 days b)18 days c)16 days d)4 days

15.X is 3 times as fast as Y and is able to complete the work in 40 days less than Y.Find the time in which they can complete the work together?
a)12 days b)17 days c)19 days d)15 days

16.Sita can finish some work in 12 days working 4 hours a day. Gita can finish the same in 15 days working 3 hours a day.In how many days can they finish it working together at 4 1/2 hours a day?
a)5 5/31 days b)5 5/32 days c)5 5/33 days d)5 5/34 days

17.A alone can do a work in 12 days and B alone in 18 days.If C takes twice as long as A and B together,how long will B and C together take to complete the same work?
a)5 days b)6 days c)8 days d)4 days

18.A and B each working alone can do a work in 10 and 15 days respectively.They started the work together but B left after sometime and A finished the remaining work in 5 days.After how many days from the start did B leave?
a)4 days b)3 days c)2 days d)8 days

19.A contractor decided to complete the work in 40 days and employed 60 men at the beginning and 40 men additionally after 10 days and got the work completed as per schedule.If he had not employed the additional men,how many extra days would he have needed to complete the work?
a)30 days b)20 days c)40 days d)45 days

20.A group of 35 men is employed to complete some work in 48 days.After 33 days,5 more men are employed and the work is finished 1 day earlier.If 5 more men were not employed,how many more days would it have taken beyond the expected period?
a)7 day behind schedule
b)3 day behind schedule
c)2 day behind schedule
d)1 day behind schedule

Share |

Labels:

Time and Work problems

Posted by Ravi Kumar at Monday, November 24, 2008
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Time and Work problems

Time and Work problems



Problems:


1)If 9 men working 6 hours a day can do a work in 88 days. Then 6 men
working 8 hours a day can do it in how many days?

Sol: From the above formula i.e (m1*t1/w1)=(m2*t2/w2)
so (9*6*88/1)=(6*8*d/1)
on solving, d=99 days.
2)If 34 men completed 2/5th of a work in 8 days working 9 hours a day.
How many more man should be engaged to finish the rest of the work in
6 days working 9 hours a day?

Sol: From the above formula i.e (m1*t1/w1)=(m2*t2/w2)
so, (34*8*9/(2/5))=(x*6*9/(3/5))
so x=136 men
number of men to be added to finish the work=136-34=102 men

3)If 5 women or 8 girls can do a work in 84 days. In how many days can
10 women and 5 girls can do the same work?

Sol: Given that 5 women is equal to 8 girls to complete a work
so, 10 women=16 girls.
Therefore 10women +5girls=16girls+5girls=21girls.
8 girls can do a work in 84 days
then 21 girls ---------------?
answer= (8*84/21)=32days.
Therefore 10 women and 5 girls can a work in 32days

4)Worker A takes 8 hours to do a job. Worker B takes 10hours to do the
same job. How long it take both A & B, working together but independently,
to do the same job?

Sol: A's one hour work=1/8.
B's one hour work=1/10
(A+B)'s one hour work=1/8+1/10 =9/40
Both A & B can finish the work in 40/9 days

5)A can finish a work in 18 days and B can do the same work in half the
time taken by A. Then, working together, what part of the same work they
can finish in a day?

Sol: Given that B alone can complete the same work in days=half the time
taken by A=9days
A's one day work=1/18
B's one day work=1/9
(A+B)'s one day work=1/18+1/9=1/6

6)A is twice as good a workman as B and together they finish a piece of
work in 18 days.In how many days will A alone finish the work.

Sol: if A takes x days to do a work then
B takes 2x days to do the same work
=>1/x+1/2x=1/18
=>3/2x=1/18
=>x=27 days.
Hence, A alone can finish the work in 27 days.

7)A can do a certain work in 12 days. B is 60% more efficient than A. How
many days does B alone take to do the same job?

Sol: Ratio of time taken by A&B=160:100 =8:5
Suppose B alone takes x days to do the job.
Then, 8:5::12:x
=> 8x=5*12
=> x=15/2 days.

8)A can do a piece of work n 7 days of 9 hours each and B alone can do it
in 6 days of 7 hours each. How long will they take to do it working together
8 2/5 hours a day?

Sol: A can complete the work in (7*9)=63 days
B can complete the work in (6*7)=42 days
=> A's one hour's work=1/63 and
B's one hour work=1/42
(A+B)'s one hour work=1/63+1/42=5/126
Therefore, Both can finish the work in 126/5 hours.
Number of days of 8 2/5 hours each=(126*5/(5*42))=3days

9)A takes twice as much time as B or thrice as much time to finish a piece
of work. Working together they can finish the work in 2 days. B can do the
work alone in ?

Sol: Suppose A,B and C take x,x/2 and x/3 hours respectively finish the
work then 1/x+2/x+3/x=1/2
=> 6/x=1/2
=>x=12
So, B takes 6 hours to finish the work.

10)X can do ¼ of a work in 10 days, Y can do 40% of work in 40 days and Z
can do 1/3 of work in 13 days. Who will complete the work first?

Sol: Whole work will be done by X in 10*4=40 days.
Whole work will be done by Y in (40*100/40)=100 days.
Whole work will be done by Z in (13*3)=39 days
Therefore,Z will complete the work first.




Complex Problems

1)A and B undertake to do a piece of workfor Rs 600.A alone can do it in
6 days while B alone can do it in 8 days. With the help of C, they can finish
it in 3 days, Find the share of each?

Sol: C's one day's work=(1/3)-(1/6+1/8)=1/24
Therefore, A:B:C= Ratio of their one day’s work=1/6:1/8:1/24=4:3:1
A's share=Rs (600*4/8)=300
B's share= Rs (600*3/8)=225
C's share=Rs[600-(300+225)]=Rs 75

2)A can do a piece of work in 80 days. He works at it for 10 days & then B alone
finishes the remaining work in 42 days. In how much time will A and B, working
together, finish the work?

Sol: Work done by A in 10 days=10/80=1/8
Remaining work=(1-(1/8))=7/8
Now, work will be done by B in 42 days.
Whole work will be done by B in (42*8/7)=48 days
Therefore, A's one day's work=1/80
B’s one day's work=1/48
(A+B)'s one day's work=1/80+1/48=8/240=1/30
Hence, both will finish the work in 30 days.

3)P,Q and R are three typists who working simultaneously can type 216 pages
in 4 hours In one hour , R can type as many pages more than Q as Q can type more
than P. During a period of five hours, R can type as many pages as P can
during seven hours. How many pages does each of them type per hour?

Sol:Let the number of pages typed in one hour by P, Q and R be x,y and z
respectively
Then x+y+z=216/4=54 ---------------1
z-y=y-x => 2y=x+z -----------2
5z=7x => x=5x/7 ---------------3
Solving 1,2 and 3 we get x=15,y=18, and z=21

4)Ronald and Elan are working on an assignment. Ronald takes 6 hours to
type 32 pages on a computer, while Elan takes 5 hours to type 40 pages.
How much time will they take, working together on two different computers
to type an assignment of 110 pages?

Sol: Number of pages typed by Ronald in one hour=32/6=16/3
Number of pages typed by Elan in one hour=40/5=8
Number of pages typed by both in one hour=((16/3)+8)=40/3
Time taken by both to type 110 pages=110*3/40=8 hours.

5)Two workers A and B are engaged to do a work. A working alone takes 8 hours
more to complete the job than if both working together. If B worked alone,
he would need 4 1/2 hours more to compete the job than they both working
together. What time would they take to do the work together.

Sol: (1/(x+8))+(1/(x+(9/2)))=1/x
=>(1/(x+8))+(2/(2x+9))=1/x
=> x(4x+25)=(x+8)(2x+9)
=> 2x2 =72
=> x2 = 36
=> x=6
Therefore, A and B together can do the work in 6 days.

6)A and B can do a work in12 days, B and C in 15 days, C and A in 20 days.
If A,B and C work together, they will complete the work in how many days?

Sol: (A+B)'s one day's work=1/12;
(B+C)'s one day's work=1/15;
(A+C)'s one day's work=1/20;
Adding we get 2(A+B+C)'s one day's work=1/12+1/15+1/20=12/60=1/5
(A+B+C)'s one day work=1/10
So, A,B,and C together can complete the work in 10 days.

7)A and B can do a work in 8 days, B and C can do the same wor in 12 days.
A,B and C together can finish it in 6 days. A and C together will do it in
how many days?

Sol: (A+B+C)'s one day's work=1/6;
(A+B)'s one day's work=1/8;
(B+C)'s one day's work=1/12;
(A+C)'s one day's work=2(A+B+C)'s one day's work-((A+B)'s one day
work+(B+C)'s one day work)
= (2/6)-(1/8+1/12)
=(1/3)- (5/24)
=3/24
=1/8
So, A and C together will do the work in 8 days.

8)A can do a certain work in the same time in which B and C together can do it.
If A and B together could do it in 10 days and C alone in 50 days, then B alone
could do it in how many days?

Sol: (A+B)'s one day's work=1/10;
C's one day's work=1/50
(A+B+C)'s one day's work=(1/10+1/50)=6/50=3/25
Also, A's one day's work=(B+C)’s one day's work
From i and ii ,we get :2*(A's one day's work)=3/25
=> A's one day's work=3/50
B's one day’s work=(1/10-3/50)
=2/50
=1/25
B alone could complete the work in 25 days.

9) A is thrice as good a workman as B and therefore is able to finish a job
in 60 days less than B. Working together, they can do it in:

Sol: Ratio of times taken by A and B=1:3.
If difference of time is 2 days , B takes 3 days
If difference of time is 60 days, B takes (3*60/2)=90 days
So, A takes 30 days to do the work=1/90
A's one day's work=1/30;
B's one day's work=1/90;
(A+B)'s one day's work=1/30+1/90=4/90=2/45
Therefore, A&B together can do the work in 45/2days


10) A can do a piece of work in 80 days. He works at it for 10 days and then
B alone finishes the remaining work in 42 days. In how much time will A&B,
working together, finish the work?

Sol: Work Done by A n 10 days =10/80=1/8
Remaining work =1-1/8=7/8
Now 7/8 work is done by B in 42 days
Whole work will be done by B in 42*8/7= 48 days
=> A's one day's work =1/80 and
B's one day's work =1/48
(A+B)'s one day's work = 1/80+1/48 = 8/240 = 1/30
Hence both will finish the work in 30 days.

11) 45 men can complete a work in 16 days. Six days after they started working,
so more men joined them. How many days will they now take to complete the
remaining work?

Sol: M1*D1/W1=M2*D2/W2
=>45*6/(6/16)=75*x/(1-(6/16))
=> x=6 days

12)A is 50% as efficient as B. C does half the work done by A&B together. If
C alone does the work n 40 days, then A,B and C together can do the work in:

Sol: A's one day's work:B's one days work=150:100 =3:2
Let A's &B's one day's work be 3x and 2x days respectively.
Then C's one day's work=5x/2
=> 5x/2=1/40
=> x=((1/40)*(2/5))=1/100
A's one day's work=3/100
B's one day's work=1/50
C's one day's work=1/40
So, A,B and C can do the work in 13 1/3 days.

13)A can finish a work in 18 days and B can do the same work in 15 days. B
worked for 10 days and left the job. In how many days A alone can finish the
remaining work?

Sol: B's 10 day's work=10/15=2/3
Remaining work=(1-(2/3))=1/3
Now, 1/18 work is done by A in 1 day.
Therefore 1/3 work is done by A in 18*(1/3)=6 days.

14)A can finish a work in 24 days, B n 9 days and C in 12 days. B&C start the
work but are forced to leave after 3 days. The remaining work done by A in:

Sol: (B+C)'s one day's work=1/9+1/12=7/36
Work done by B & C in 3 days=3*7/36=7/12
Remaining work=1-(7/12)=5/12
Now , 1/24 work is done by A in 1 day.
So, 5/12 work is done by A in 24*5/12=10 days

15)X and Y can do a piece of work n 20 days and 12 days respectively. X started
the work alone and then after 4 days Y joined him till the completion of work.
How long did the work last?

Sol: work done by X in 4 days =4/20 =1/5
Remaining work= 1-1/5 =4/5
(X+Y)'s one day's work =1/20+1/12 =8/60=2/15
Now, 2/15 work is done by X and Y in one day.
So, 4/5 work will be done by X and Y in 15/2*4/5=6 days
Hence Total time taken =(6+4) days = 10 days

16)A does 4/5 of work in 20 days. He then calls in B and they together finish
the remaining work in 3 days. How long B alone would take to do the whole work?

Sol: Whole work is done by A in 20*5/4=25 days
Now, (1-(4/5)) i.e 1/5 work is done by A& B in days.
Whole work will be done by A& B in 3*5=15 days
=>B's one day's work= 1/15-1/25=4/150=2/75
So, B alone would do the work in 75/2= 37 ½ days.

17) A and B can do a piece of work in 45 days and 40 days respectively. They
began to do the work together but A leaves after some days and then B completed
the remaining work n 23 days. The number of days after which A left the work was

Sol: (A+B)'s one day's work=1/45+1/40=17/360
Work done by B in 23 days=23/40
Remaining work=1-(23/40)=17/40
Now, 17/360 work was done by (A+B) in 1 day.
17/40 work was done by (A+B) in (1*(360/17)*(17/40))= 9 days
So, A left after 9 days.

18)A can do a piece of work in 10 days, B in 15 days. They work for 5 days.
The rest of work finished by C in 2 days. If they get Rs 1500 for the whole
work, the daily wages of B and C are

Sol: Part of work done by A= 5/10=1/2
Part of work done by B=1/3
Part of work done by C=(1-(1/2+1/3))=1/6
A's share: B's share: C's share=1/2:1/3:1/6= 3:2:1
A's share=(3/6)*1500=750
B's share=(2/6)*1500=500
C's share=(1/6)*1500=250
A's daily wages=750/5=150/-
B's daily wages=500/5=100/-
C's daily wages=250/2=125/-
Daily wages of B&C = 100+125=225/-

19)A alone can complete a work in 16 days and B alone can complete the same
in 12 days. Starting with A, they work on alternate days. The total work will
be completed in how many days?

(a) 12 days (b) 13 days (c) 13 5/7 days (d)13 ¾ days

Sol: (A+B)'s 2 days work = 1/16 + 1/12 =7/48
work done in 6 pairs of days =(7/48) * 6 = 7/8
remaining work = 1- 7/8 = 1/8
work done by A on 13th day = 1/16
remaining work = 1/8 – 1/16 = 1/16
on 14th day, it is B’s turn
1/12 work is done by B in 1 day.
1/16 work is done by B in ¾ day.
Total time taken= 13 ¾ days.
So, Answer is: D

20)A,B and C can do a piece of work in 20,30 and 60 days respectively. In how
many days can A do the work if he is assisted by B and C on every third day?

Sol: A's two day's work=2/20=1/10
(A+B+C)'s one day's work=1/20+1/30+1/60=6/60=1/10
Work done in 3 days=(1/10+1/10)=1/5
Now, 1/5 work is done in 3 days
Therefore, Whole work will be done in (3*5)=15 days.

21)Seven men can complete a work in 12 days. They started the work and after
5 days, two men left. In how many days will the work be completed by the
remaining men?

(A) 5 (B) 6 (C ) 7 (D) 8 (E) none

Sol: 7*12 men complete the work in 1 day.
Therefore, 1 man's 1 day's work=1/84
7 men's 5 days work = 5/12
=>remaining work = 1-5/12 = 7/12
5 men's 1 day's work = 5/84
5/84 work is don by them in 1 day
7/12 work is done by them in ((84/5) * (7/12)) = 49/5 days = 9 4/5 days.
Ans: E

22).12 men complete a work in 9 days. After they have worked for 6 days, 6 more
men joined them. How many days will they take to complete the remaining work?

(a) 2 days (b) 3 days (c) 4 days (d) 5days

Sol : 1 man's 1 day work = 1/108
12 men's 6 days work = 6/9 = 2/3
remaining work = 1 – 2/3 = 1/3
18 men's 1 days work = 18/108 = 1/6
1/6 work is done by them in 1 day
therefore, 1/3 work is done by them in 6/3 = 2 days.
Ans : A

23).A man, a woman and a boy can complete a job in 3,4 and 12 days respectively.
How many boys must assist 1 man and 1 woman to complete the job in ¼ of a day?

(a). 1 (b). 4 (c). 19 (d). 41

Sol : (1 man + 1 woman)'s 1 days work = 1/3+1/4=7/12
Work done by 1 man and 1 women n 1/4 day=((7/12)*(1/4))=7/48
Remaining work= 1- 7/48= 41/48
Work done by 1 boy in ¼ day= ((1/12)*(1/4)) =1/48
Therefore, Number of boys required= ((41/48)*48)= 41 days
So,Answer: D

24)12 men can complete a piece of work in 4 days, while 15 women can complete
the same work in 4 days. 6 men start working on the job and after working for
2 days, all of them stopped working. How many women should be put on the job
to complete the remaining work, if it is to be completed in 3 days.

(A) 15 (B) 18 (C) 22 (D) data inadequate

Sol: one man's one day's work= 1/48
one woman's one day's work=1/60
6 men's 2 day's work=((6/48)*2)= ¼
Remaining work=3/4
Now, 1/60 work s done in 1 day by 1 woman.
So, ¾ work will be done in 3 days by (60*(3/4)*(1/3))= 15 woman.
So, Answer: A

25)Twelve children take sixteen days to complete a work which can be completed
by 8 adults in 12 days. Sixteen adults left and four children joined them. How
many days will they take to complete the remaining work?

(A) 3 (B) 4 ( C) 6 (D) 8

Sol: one child's one day work= 1/192;
one adult's one day's work= 1/96;
work done in 3 days=((1/96)*16*3)= 1/2
Remaining work= 1 – ½=1/2
(6 adults+ 4 children)'s 1 day's work= 6/96+4/192= 1/12
1/12 work is done by them in 1 day.
½ work is done by them 12*(1/2)= 6 days
So, Answer= C

26)Sixteen men can complete a work in twelve days. Twenty four children can
complete the same work in 18 days. 12 men and 8 children started working and
after eight days three more children joined them. How many days will they now
take to complete the remaining work?

(A) 2 days (B) 4 days ( C) 6 days (D) 8 days

ol: one man's one day's work= 1/192
one child's one day's work= 1/432
Work done in 8 days=8*(12/192+ 8/432)=8*(1/16+1/54) =35/54
Remaining work= 1 -35/54= 19/54
(12 men+11 children)'s 1 day's work= 12/192 + 11/432 = 19/216
Now, 19/216 work is done by them in 1 day.
Therefore, 19/54 work will be done by them in ((216/19)*(19/54))= 4 days
So,Answer: B

27)Twenty-four men can complete a work in 16 days. Thirty- two women can
complete the same work in twenty-four days. Sixteen men and sixteen women
started working and worked for 12 days. How many more men are to be added to
complete the remaining work in 2 days?

(A) 16 men (B) 24 men ( C) 36 men (D) 48 men

Sol: one man's one day's work= 1/384
one woman's one day's work=1/768
Work done in 12 days= 12*( 16/384 + 16/768) = 12*(3/48)=3/4
Remaining work=1 – ¾=1/4
(16 men+16 women)'s two day's work =12*( 16/384+16/768)=2/16=1/8
Remaining work = 1/4-1/8 =1/8
1/384 work is done n 1 day by 1 man.
Therefore, 1/8 work will be done in 2 days in 384*(1/8)*(1/2)=24men

28)4 men and 6 women can complete a work in 8 days, while 3 men and 7 women
can complete it in 10 days. In how many days will 10 women complete it?

(A) 35 days (B) 40 days ( C) 45 days (D) 50 days

Sol: Let 1 man's 1 day's work =x days and
1 woman's 1 day's work=y
Then, 4x+6y=1/8 and 3x+7y=1/10.
Solving these two equations, we get: x=11/400 and y= 1/400
Therefore, 1 woman's 1 day's work=1/400
=> 10 women will complete the work in 40 days.
Answer: B

29)One man,3 women and 4 boys can do a piece of work in 96hrs, 2 men and 8 boys
can do it in 80 hrs, 2 men & 3 women can do it in 120hr. 5Men & 12 boys can do
it in?

(A) 39 1/11 hrs (B) 42 7/11 hrs ( C) 43 7/11 days (D) 44hrs

Sol: Let 1 man's 1 hour's work=x
1 woman's 1 hour's work=y
1 boy's 1 hour's work=z
Then, x+3y+4z=1/96 -----------(1)
2x+8z= 1/80 ----------(2)
adding (2) & (3) and subtracting (1)
3x+4z=1/96 ---------(4)
From (2) and (4), we get x=1/480
Substituting, we get : y=1/720 and z= 1/960
(5 men+ 12 boy)'s 1 hour's work=5/480+12/960 =1/96 + 1/80=11/480
Therefore, 5 men and 12 boys can do the work in 480/11 or 43 7/11hours.
So,Answer: C